Escher Construction Update - May 2016

With the ever improving spring weather, construction of Escher on Broughton in Downtown Victoria has really hit its stride. Since our last update, the Campbell Construction crew has poured the first six floors and are currently working on the formwork for level 7. Finish work is underway on the underground parkade and curbs are being installed above grade to accept windows and exterior doors within the coming weeks. The team is pouring a new floor every nine to ten business days which means that in no time at all, the superstructure will reach its full height!

This also means that Escher is on track to be move in ready in Early 2017…less than eight months from now! We’ve just added some new construction photos to our Gallery so be sure to check them out.

Looking for more frequent updates? Check out our Live Site Cam! The camera was moved up the crane mast earlier this month to provide a better view of the work below. It’s quite a view from up there!