January Elenore Construction Update

Now that the holiday decorations have been put away and New Year’s resolutions are in full swing, we are excited to kick off 2019 with a construction update on Elenore on Fifth.

The team has been hard at work with approximately 60 workers on site each workday. Excavation was completed October 5, 2018 and the site has been active with concrete pouring. Levels P2 and P1 have both been poured and we anticipate reaching grade in February. Construction scaffolding and site trailers are now positioned over the sidewalk on Main Street to provide easier access to the site and to safely allow pedestrians to navigate the shops along Main.

Over the coming months, Elenore will begin to rise and take its proud home along the Mount Pleasant slope. Stay tuned for more construction and project updates.