Quarterly Construction Update

Spring is in the air with cherry blossoms lining the streets and new growth all around, and we’ve seen construction at all our projects really hit a stride. With the completion of 34|W7 in January and nearly 600 homes under construction, we have lots of progress to share.

Elenore on Fifth

Elenore on Fifth is quickly taking shape. With 50-60 workers on site daily, the parkade reached grade in late January and we have seen the building structure rise above the street, climbing higher with each passing week. The formwork and concrete pours for the townhomes were completed in early February and floors sixth and seventh completed as of April 19. At this pace, we should see Elenore reach its full height by May. For live updates check out site camera one and camera two.

Yates on Yates & Vivid at the Yates

With 5,000 m3 of concrete poured to date and an average of 50 workers on site daily, both the Yates on Yates and Vivid at the Yates are well on their way! In fact, Chard had our largest single concrete pour to date in March with 334m3 of concrete on site – that’s equivalent to 83,500 jugs of milk! The Yates on Yates P1 & P2 were poured earlier this quarter and construction has now reached Level 2, with townhomes underway and Level 4 expected to be complete by mid May. The Vivid crane was installed in January and construction has now reached parking level 1. For live site camera updates click here!

1441 St. Georges

Our two-tower, purpose-built rental project in North Vancouver continues to take shape with 80 workers on site daily. Once complete, this project will add 256 homes to the Central Lonsdale community. Over the last quarter, the East Tower has seen the framing of interior walls, window installation, and plumbing and electrical have all begun. On the West Tower, excavation is nearly complete, and the crane was installed in early March. With so much activity, we look forward to sharing more details about this development with you in the coming months.